Welder’s Test Position (ASME IX QW-461.3-461.7)


Groove Welds in Plate – Test Positions

  • 1G – Flat Position. Plate in horizontal plane with the weld metal deposited from above
  • 2G – Horizontal Position. Plate in a vertical plane with the axis of the weld horizontal
  • 3G – Vertical Position. Plate in a vertical plane with the axis of the weld vertical
  • 4G – Overhead Position. Plate in a horizontal plane with the weld metal deposited from underneath

Groove Welds in Pipe – Test Positions

  • 1G (rotated) – Flat Position. Pipe with its axis horizontal and rolled during welding so that the weld metal is deposited from above
  • 2G – Horizontal Position. Pipe with its axis vertical and the axis of the weld in a horizontal plane. Pipe shall not be rotated during welding
  • 5G – Multiple Position. Pipe with its axis horizontal and with the welding groove in a vertical plane. Welding shall be done without rotating the pipe
  • 6G – Multiple Position. Pipe with its axis inclined in 45 degrees to horizontal. Welding shall be done without rotating the pipe.

Fillet Welds in Plate – Test Positions

  • 1F – Flat Position. Plates so placed that the weld is deposited with its axis horizontal and its throat vertical.
  • 2F – Horizontal. Plates so placed that the weld is deposited with its axis horizontal on the upper side of the horizontal surface and against vertical surfacde.
  • 3F – Vertical Position. Plates so placed that the weld is deposited with its axis vertical.
  • 4F – Overhead Position. Plates so placed that the weld is deposited with its axis horizontal on the underside of the horizontal surface and against the vertical surface.

Fillet Welds in Pipe- Test Positions

  • 1F (rotated) – Flat Position – Pipe with its axis incline at 45 degrees to horizontal and rotated during welding so that weld metal is deposited from above and at the point of deposition the axis of the weld is horizontal and the throat vertical
  • 2F – Horizontal Position. Pipe with its axis vertical so that the weld is deposited on the upper side of the horizontal surface against the vertical surface. The axis of the weld will be horizontal and the pipe is not rotated during welding
  • 2FR – Horizontal Position (Rotated). Pipe with its axis horizontal and the axis of the deposited weld in the vertical plane. The pipe is rotated during welding.
  • 4F – Overhead Position – Pipe with its axis vertical so that the weld is deposited on the underside of the horizontal surface against the vertical surface. The axis of the weld will be horizontal and the pipe is not rotated during welding.
  • 5F – Multiple Position. Pipe with its axis horizontal and the axis of the deposited weld in the vertical plane. The pipe is not rotated during welding.

Stud Welds – Test Positions

  • 1S, 2S & 4S

Responses

  1. Welding foreman

  2. am a pipeline welding student about to graduate pls am looking for where i can my I.T and employment also

  3. Super unbeliveable welding

  4. am interested of your institute sir want
    to know if you got online courses


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: